Menu

Bill of Quantities

Foundations

Project ID: 46 - Foundation 1

Item No. Description Unit Quantity Rate (Ksh) Total (Ksh)
1. Excavation
1.1 Strip Footing Excavation 270.00 525.00 141,750.00
1.2 Pad Footing Excavation 0.38 525.00 201.60
Total Excavation141,951.60
2. Concrete Works
2.1Strip Footing Concrete36.00-455,400.00
2.2Pad Footing Concrete0.13-1,619.20
Total Concrete457,019.20
3. Reinforcement
3.1Strip Footing Barskg1,598.70-271,778.44
3.2Pad Footing Barskg3.16-536.63
Total Reinforcement272,315.07
4. Masonry
4.1BricksPieces544960.00326,940.00
5. Mortar
5.1Mortar Volume27.258,000.00217,992.96
6. Summary
6.1Total Cement BagsBags344.84--
6.2Total Fine Aggregates (Sand)Lorries8.98--
6.3Total Coarse Aggregates (Ballast)Lorries3.87--
6.4Labor---424,865.65
6.5Material Cost---1,416,218.83
Total Cost 1,841,084.48
Edit

Ground Floor

Project ID: 46

Description Unit Quantity Unit Rate (Ksh) Total (Ksh)
Substructure
Hardcore Blinding 28.00 1,400.00 39,200.00
Murram Blinding 14.00 800.00 11,200.00
Damp Proof Course (DPC) Item 1 14,000.00 14,000.00
BRC Mesh Item 1 42,000.00 42,000.00
Concrete Work
Concrete Work 14.00 12,650.00 177,100.00
Screed Mortar 2.80 8,000.00 22,400.00
Total Cement Bags Bags 77.76 - -
Total Fine Aggregates (Sand) Lorries 2.03 - -
Total Coarse Aggregates (Ballast) Lorries 1.50 - -
Finishes
Floor Tiles Pcs 1,556.00 180.00 280,080.00
Other Costs
Labor Item 1 117,196.00 117,196.00
Total Material Cost Item 1 585,980.00 585,980.00
Total Cost 703,176.00
Edit

Walls

Add Wall Item
Item Description Unit Quantity Rate (Ksh) Amount (Ksh) Actions
1 Bricks for Wall1 No. 6,267 40.00 250,680.00
2 Mortar (Volume: 31.618 m³) 31.618 8,000.00 252,943.36
3 Cement Bags for Mortar Bags 227.65 - -
4 Sand (Fine Aggregate) - Lorry (FSR) Lorry 5.93 - -
5 Windows (Type 1: 10, Type 2: 0) No. 10.00 - 40,000.00
6 Doors (Type 1: 2, Type 2: 0) No. 2.00 - 16,000.00
Total Cost for Wall1 Ksh 727,510.37

Summary Totals

Total Cement Bags: 227.65

Total Sand (FSR Lorry): 5.93

Total Bricks: 6,267.00

Total Brick Cost: Ksh 250,680.00

Total Mortar Cost: Ksh 252,943.36

Total Labor Cost: Ksh 167,887.01

Grand Total Cost: Ksh 727,510.37

Interior Walls With Doors

No interior walls created.

Total Walls Analysis (Including Exterior Walls)

Total Cement Bags: 227.65

Total Fine Aggregate (FSR Lorry): 5.93

Total Bricks: 6,267.00

Total Bricks Cost: Ksh250,680.00

Total Mortar Cost: Ksh252,943.36

Total Walls Cost: Ksh727,510.37

Slab Panels

No slabs created.

Beams

Create Beam
Beam: Beam 1 (ID: 46)
Item Description Unit Quantity Rate (Ksh) Total (Ksh)
Concrete Works
Concrete Volume 2.61 - -
Cement Bags Bags 10.74 - -
Fine Aggregates (Sand) Lorry 0.28 - -
Coarse Aggregates (Ballast) Lorry 0.28 - -
Concrete Cost 2.61 6,000.00 15,660.00
Reinforcement
Main Bars (12mm Ø) bars 9.67 - 14,418.00
Support Bottom Bars (0mm Ø) bars 0.00 - 0.00
Top Bars (12mm Ø) bars 9.67 - 14,418.00
Support Top Bars (0mm Ø) bars 0.00 - 0.00
Links (8mm Ø) bars 14.58 - 9,661.78
Total Reinforcement Cost kg 274.99 140.00 38,497.99
Labor & Formwork
Labor Sum 1 - 23,294.40
Formwork Sum 1 - 23,490.00
Total Material Cost 77,647.99
Grand Total 100,942.38

Total Cost for All Beams: Ksh 100,942.38

Columns

No columns created.

Hipped Roofs

No hipped roof data available.

Gable Roof

Project ID Item Description Unit Quantity Unit Rate (Ksh) Total (Ksh) Actions
46 1 Truss Materials m 428,000.00 150.00 64,200.00
2 Purlins m 800.00 100.00 22,200.00
3 Roofing Sheets (338 pcs) pcs 338 800.00 270,419.75
4 Labor sum 1 107,045.93 107,045.93
Grand Total - Truss Cost Ksh 64,200.00
Grand Total - Purlins Ksh 22,200.00
Grand Total - Roofing Sheets Ksh 270,419.75
Grand Total - Labor Ksh 107,045.93
Overall Gable Roof Total Ksh 463,865.68

Grand Total Cost Summary

Grand Cement Bags:

660.99

Grand Fine Agg (Sand) FSR Lorry:

Ksh 17.21

Grand Coarse Agg (Ballast) FSR Lorry:

Ksh 5.65

Grand Concrete Cost:

Ksh 472,679.20

Grand Bars Cost:

Ksh 310,813.06

Grand Labor Cost:

Ksh 840,288.98


Grand Total Cost

Ksh 3,836,578.91